This week we continue building our landscape patch attribute table, providing our decision makers with more data on which to base their landscape prioritization of pronghorn antelope habitat. Here we examine habitat patches not as isolated entities but as components of a larger, connected network of habitat zones.
The general notion here is this: critters such as the pronghorn aren't necessarily restricted to areas classified as habitat. They may venture beyond these zones, perhaps wandering into hostile terrain to get to other habitat patches. As such, we should not limit our analyses to the resource characteristics of a single patch, but rather to the network of patches that an individual could potentially travel to, i.e. the habitat patches that are functionally connected.
In this exercise, we explore different ways of characterizing connectivity using geospatial analysis. As in other exercises, we must make certain assumptions to perform these analyses. First, we need a proper habitat patch map, which we have from the previous lab. And second, we'll need to estimate how far a pronghorn is likely to venture outside its habitat as this will be the criteria for deciding whether a pair patches are functionally connected. This can be either a Euclidean distance, or, if data are available on how far an antelope is likely to travel in specific landscape types (e.g. across intact forest vs. open field), a cost-weighted distance.
With our habitat patch raster and cost surface datasets, we can evaluate connectivity within our landscape. We begin with a simple hypothetical situation where we look at the distance each habitat patch is to a single source patch. This source patch could represent a variety of things: an established pronghorn reserve, a well-known successful breeding ground for pronghorn -- anything really that we'd want other patches to be linked with. Calculating the distance other patches fall from this source patch gives us one means of ranking patches in terms of connectivity.
We'll also calculate least-cost paths (LCPs) from all patches to this central source patch. This reveals areas of non-habitat that we may want to protect based on the assumption that these areas could be pronghorn migration paths.
Noting that LCPs are somewhat restrictive (are pronghorn really that likely to locate and use the single least-costly path?), we'll also look at how corridors are calculated in ArcGIS. While simple to execute, corridor calculations are quite CPU intensive, and we'll be limited here to calculating a corridor between a single pair of patches. A complete corridor map would require us to calculate corridors between all pairs of patches, or about 120,000 patch pairs ( , when , in our case, is 345).
Next, we look at habitat patch subnetworks -- sets of patches that are functionally connected to each other. A landscape may have a single large patch in one remote corner that might, at first, appear as the best single habitat resource available to the pronghorn, but if several smaller patches in another corner of the landscape comprise an even larger sub-network of patches, then protecting these patches may actually provide more resources for our target species. Identifying patch subnetworks allows us to visualize the landscape more accurately as resource pools, allow us to perhaps prioritize the individual patches that comprise the larger networked resource pools for conservation.
With patch subnetworks established, we can then begin to examine attributes of the subnetworks and of the patches of which they are comprised. The robustness of a patch subnetwork depends heavily on the connectivity of the patches within: some subnetworks may completely rely on a single patch to maintain interconnectivity. we'll examine a metric called centrality that reflects the contribution of a single patch to keeping the subnetwork connected.
In the end, we'll actually have created a dataset from which we can calculate several other connectivity metrics, but as you'll see, we start hitting the wall of ArcGIS' usability. For more in-depth analyses, software packages such as NetworkX (http://networkx.lanl.gov/) or CircuitScape (http://www.circuitscape.org/), are available and we will examine demonstrations in class if time permits...
The simplest way to calculate distances between patches would be to compute Euclidean distances from each patch. Euclidean distance, however, assumes that our antelope can wander outside its habitat with equal risk regardless of what it's wandering into: an individual travelling through 1 km of uninhabited woodland to get to the source patch has the same chance of success as one travelling across difficult or dangerous terrain.
To reflect the notion that that pronghorn are likely to travel more easily across some areas than others, we replace Euclidean distance approach with a cost distance one. The catch here, of course, is that to do this, we need a resistance surface where cell values reflect the various costs pronghorn are likely to incur travelling across a given cell. As you can guess, these data can be very speculative -- not that that will stop us, but it's yet another factor to remember when we assemble our model.
In lecture, we discussed a few approaches to creating resistance surfaces. One is a simple recoding of a dominant overstory vegetation map into travel costs using expert-based estimates of the relative resistances that each cover type will impose on the pronghorn. A second widely used approach is to invert a habitat suitability raster. (See Beier's Corridor Designer web site...).
Inverting a habitat suitability surface, however, can be done a few ways. One method is to divide 1 by the suitability values; this approach generates a curved relationship where resistances drop sharply as habitat suitability moves from 0 to 1 (figure below on left). Another important consideration when using this approach is that pixels with a habitat suitability of zero will have infinite cost, that is, they will be absolute barriers (and will be coded as NoData in raster datasets). This may be desirable (e.g. when roads or water bodies are impenetrable to our focal species), but it can cause problems when generating cost surfaces. A solution is to first code all zero-value pixels into a low value (e.g. 0.001) before dividing one by the values.
Figure 1. Relationship between resistance value and habitat suitability using different methods of inversion. The graph on the top represents ; the graph on the bottom represents .
Another method, the one recommended by Beier, is to subtract habitat suitability values by the maximum suitability value, or 1.0 in our pronghorn example. This approach generates a linear relationship between suitability and resistance (right side of above figure). One potential issue with this approach, however, is that some pixels (those with maximum habitat suitability) will have zero resistance. While this too may be desirable, it too can cause issues when calculating cost surfaces, and some packages (e.g. Circuitscape) do not allow zero resistance surfaces. A solution to this is to assign a very low cost to zero resistance pixels.
Our cost layer will be an inverse of the Habitat Suitability values, which range from 0 (inhospitable) to 1 (happy pronghorn). We will use the second approach mentioned above to invert habitat suitability and assign a minimum cost of 0.0001 to cells where habitat suitability is 1.0 (to avoid zero cost pixels).
Why do we use
0.0001
as the minimum value? Well, we want some non-zero value, but also something that is smaller than any existing non-zero value. Try the above procedure, setting zero values to 0.001. In the result, you'll see some values of 9.64 x 10-5. That means that our zero values (now set to 0.001) are not the least cost cells.
In this step, we'll calculate the cost-weighted distance from each patch to a source patch. This source patch could represent an existing protected area, a noted pronghorn breeding ground, or any spatial feature to which it's advantageous to be closer. we'll use patch 76 -- a large central patch -- as our source patch in this example and calculate the least cost distance a pronghorn would have to travel to get to this patch... (Note that the assignment asks you to do this for a different patch -- patch 195!)
Here we use the Cost Path tool to calculate the least-cost paths from all patches back to the source patch. We add a few steps at the end to create a topologically correct vector layer of least-cost paths that both enables us to create prettier maps and to do additional analyses with the result.
Add the Cost Path tool to your Cost Distance model created above. Set the destination to be the patch cores, and link the Cost Distance and Cost Backlink result from your previous analysis to the process. Make sure that the Path Type is set to "Each_Zone"; this tells the tool to create a least-cost path to each zone (i.e., each patch).
Question: how come the Cost Path tool doesn't need to know what our patch source is?
Examine the cost path result. The least cost paths are clear, but the attributes in this layer are a bit tricky and not very revealing. Here is the excerpt from the Desktop Help on what the attributes mean:
"Each least-cost path is assigned a value when encountered in the scanning process. The ending cell on the original source raster (from which the cost distance and back link were derived) of a cost path receives one, the first path receives three, the second four, and so forth. The value two is reserved for the merged portion of paths that have portions of a common cost path."
We'll now go beyond the least-cost paths calculated with the spatial analyst tool, using some hydrology tools (stream order, and stream to feature) to get a topologically correct vector version of our least-cost paths.
To use the hydrology tools, we first need a "flow direction" raster. The cost backlink raster we created is actually a lot like a flow direction raster, they both use integers to reflect the cardinal direction to the next cell in the travel route. The key difference is that, where the flow direction rasters use 8-bit (top line of figure) integers, the cost backlink raster uses base~10~ values (bottom row of figure).
So to convert the cost backlink raster to a flow direction raster, we take the ½ the base-2 exponent of the cost backlink. (You can just trust me on this...)
Int(Exp2("%CostBack%") / 2)
(where CostBack
is the name of your cost backlink raster).Inspect the results, ensuring that the only values in the output are 1,2,4,8,32,16,64, and 128. We'll need to set that to NoData.With our flow direction raster created, we can now use the Stream Order tool to label each least-cost path segment with a value representing how much traffic it might get. And then we convert that to a vector so we can display our result as a weighted line.
Draw the polylines result as graduated symbols using the GRID_CODE (i.e. Shreve stream order) attribute as the value. Set the symbol classification to use 6 geometric intervals. You layer should show quite clearly which routes along all the least-cost paths are [theoretically] well traveled!
►A recent update to ArcGIS Pro includes a "Cost Path as Polyline" tool, which appears to work similarly to the workflow outlined above. The result includes a least cost path, tagged with length and sum cost. In fact, it computes least costs (i.e. Step "C" above) AND the paths. However, it does not compute total traffic along a given path. )
Least-cost paths are used widely by conservationists to explore and visualize connectivity, but actual field data bears little evidence that animals truly select and use least-cost paths. So, rather than looking at the single least-cost path among patch pairs, we might want to identify a least-cost corridor of cells, i.e. all cells between two patches below a certain accumulative cost threshold.
This is done using, of all things, the "Corridor" tool in ArcGIS, and works by simply summing up two cost distance rasters, one generated from each habitat source. (In fact, simply adding the two rasters together using 'Plus' tool gives the exact same result!) The resulting cell values represent the range of accumulative costs between two sources. If all cells with values less than a maximum accumulated distance (or threshold) are selected from the corridor raster, the resulting output raster will correspond to a swath (or corridor) of cells that do not exceed a specified cost. The resultant threshold output can be viewed as the least-cost corridor of cells, not the least-cost path (a single line).
Here we create a corridor between our source patch (#76) and another large patch -- #195.
Your result should have continuous values ranging from the minimum cost to travel between the two patches up to our threshold of 300,000. View this layer as 5 quantiles, and you'll see that as the values get larger, the corridor gets wider. You should also be able to view pockets of high resistance where corridors split and rejoin.
Least-cost paths and corridors can be useful for prioritizing non-habitat areas for conservation as they indicate regions important in antelope migrations or logical places to create new habitat, but since we're concerned with habitat prioritization, we need to refocus on the role habitat patches play in connectivity, which we'll do shortly.
First, however, we should point out that our least-cost path and corridor analyses are limited to arbitrarily selected patches or patch pairs. What if we wanted to find the complete set of least-cost paths between all patch pairs. It turns out, this is not all that easy in ArcGIS because: (1) the tools involved are designed to work on single patches or patch pairs so upscaling this to examine all patch pairs would involve iterations; and (2) this stuff it incredibly CPU intensive -- to do all patch pairs would take a l-o-n-g time.
If we assume that a pronghorn antelope can actually wander outside its habitat, say for a distance of 30,000 cost units, before feeling exposed and uncomfortable, then we can also assume that two habitat patches within this distance of each other are functionally connected. Now our antelope can effectively wander from patch to patch to patch, as long as all the patches are within the cost threshold of 30,000. The set of patches connected by this threshold distance is termed a patch subnetwork, and the following analysis steps show us how to create that from our boundary cleaned habitat patch layer.
Patch subnetworks can be created using Euclidean distances or cost distances (if appropriate data are available). With our cost surfaces created, we can calculate cost distances away from habitat patches and apply a threshold to determine the extent of cost-distance derived habitat patch subnetworks. The steps below outline the process to compute subnetworks for patches using a cost distance approach. This is set for the assumption that the pronghorn can successfully travel up to 30,000 cost units outside habitat.
The final result contains your patch subnetworks, each uniquely labeled. All patches within a given subnetwork are functionally connected, implying that a pronghorn in one patch can wander to, and use the resources of any of the other patches within the subnetwork.
Subnetworks can be useful in determining conservation value because they give us a better idea of the complete pool of resources available to individuals in a given patch. For example, a single patch with 100 ha of habitat may appear more conservation-worthy than another with only 2 ha. However, if that second patch is functionally connected to 5 other 2 ha patches, then a resident antelope actually has access to 12 ha of habitat. So pooling habitat resources among patches within a subnetwork could be a better indication of conservation value for the patches making up the subnetwork.
Calculating attributes such as the amount of habitat, of core habitat, mean shape index, etc., for each subnetwork could give us an idea of which subnetworks we might prioritize for conservation and we could tag all the patches within those subnetworks with a higher priority in our patch attribute table.
ArcGIS Pro's Cost Connectivity tool appears to utility to this topic. However, this tool computes connectivity only to the patches nearest to it. If you have a patch just a bit further than a nearby one, this tool will compute distance via the patch in the middle and not directly to the current patch....
Landscape prioritization often focuses on the attributes of individual patches, losing sight of the fact that the distribution of patches within a landscape may be equally important. Connectivity analysis provides quantitative means of ranking patches based on their proximity to important source patches or on their membership to larger patch subnetworks, which may more accurately reflect the pool of resources available to individuals. And if we were looking at prioritizing non-habitat regions for conservation, connectivity analysis would tell us where migration routes between habitat patches are likely to occur, giving land managers information on where development should perhaps be avoided.
Connectivity analysis is currently one of the more vanguard applications of landscape prioritization. Applications of graph theory -- a discipline originating from study of computer based networks -- are providing us with exciting new ways (and new software approaches) to examine and quantify inter-patch relationships.
Use the steps provided in this document to help you submit the following products. All questions should be answered patch cores and the cost surface generated in lab (the inverse habitat likelihood resistance).
Numbered items should be answered in the Connectivity_Results.xlsx Excel spreadsheet. Bulleted items should be submitted separately. All maps are to simply check your work; they should clearly show what's being asked, but no points will be deducted for "lack of cartographic polish".
Pay attention to the details involved in each question; they may be different than those used in the lab...
How many boundary cleaned patches are within 100,000 cost units of Patch 195?
Which patch is furthest, cost-wise, from Patch 195? How far (rounded to the nearest thousand cost unit) is this patch from Patch 195?
Create a simple map showing the least cost paths from all patches to Patch 195 as vectors weighted by how many least-cost paths are involved in that segment (i.e., traffic calculated via the Shreve stream ordering algorithm). Use graduated symbols, breaking your lines into 6 geometric intervals with line thicknesses ranging from 0.4 to 8 pts.
Create a map showing the corridor between Patch 76 and Patch 195 thresholded at 300,000 cost units. Display the corridor cost values classified into 5 quantiles. Include a legend in or along with this map.
Create a map of functionally connected patch subnetworks based on data that a pronghorn can travel up to 40,000 cost units between patches. Show the subnetwork areas as distinct colors and show the patches on top as a single color.
To submit:
Your completed Excel spreadsheet (Connectivity_Results.xlsx)
Simple maps:
Your ArcGIS Pro toolbox file (.tbx). Do NOT submit your entire workspace.